Some products release whenever something is ready (continuous delivery). Others release on a schedule: a release train leaves the station on a fixed date, and whatever is ready by the cut-off is on it; whatever isn't waits for the next one. Browsers (Chrome and Firefox ship a new major version every four weeks), Kubernetes (three minor releases a year), Ubuntu (every six months) and most mobile apps work this way.

Why trains

Benefit Because
predictability users, support and marketing know when the next version comes
no "one more feature" delays the date is fixed; the scope adapts
a steady stabilisation window every release gets the same freeze and testing time
less pressure per feature missing a train costs one cycle, not an open-ended delay

The cost: a fix that is ready on day 2 waits for the next train unless it qualifies for a hotfix on the current release branch (Release Branches & Hotfixes). Trains need feature flags for anything that isn't finished by the cut-off (Feature Flags).

The calendar

A typical four-week train with overlapping stages: while version N is stabilising on its release branch, version N+1 is being developed on main.

week:        1    2    3    4    5    6    7    8
main:      [ develop 1.8         ][ develop 1.9         ]
                               ↓ cut release/1.8
release/1.8:                   [ beta/stabilise ] → 1.8.0 ships
                                                  ↓ cut release/1.9
release/1.9:                                      [ beta/stabilise ] → 1.9.0

This model generates the dates for a four-week train (cut on a Monday, two weeks of stabilisation, release on a Tuesday) with an extended-support release every fourth train, and decides which merged changes make which train:

python · try it yourself
from datetime import date, timedelta

def trains(first_cut, first_version, count, cycle_weeks=4, stabilise_weeks=2, lts_every=4):
    major, minor = map(int, first_version.split("."))
    out = []
    for i in range(count):
        cut = first_cut + timedelta(weeks=cycle_weeks * i)
        out.append({
            "version": f"{major}.{minor + i}.0",
            "cut": cut,
            "freeze": cut + timedelta(weeks=stabilise_weeks) - timedelta(days=3),   # Friday before release
            "release": cut + timedelta(weeks=stabilise_weeks, days=1),             # Tuesday
            "lts": (minor + i) % lts_every == 0,
        })
    return out

schedule = trains(date(2026, 1, 5), "1.8", 5)
print(f"{'version':<8} {'branch cut':<11} {'code freeze':<12} {'release':<11} support")
for t in schedule:
    print(f"{t['version']:<8} {t['cut']}  {t['freeze']}   {t['release']}  {'LTS (12 months)' if t['lts'] else '1 cycle'}")

merges = [("new export dialog", date(2026, 1, 2)), ("crash fix in sync", date(2026, 1, 5)),
          ("faster search", date(2026, 1, 6)), ("dark theme", date(2026, 2, 10)),
          ("plugin API", date(2026, 3, 2))]
print()
for name, merged in merges:
    train = next(t for t in schedule if merged < t["cut"] or merged == t["cut"])
    print(f"{name:<18} merged {merged} -> ships in {train['version']} on {train['release']}")
version  branch cut  code freeze  release     support
1.8.0    2026-01-05  2026-01-16   2026-01-20  LTS (12 months)
1.9.0    2026-02-02  2026-02-13   2026-02-17  1 cycle
1.10.0   2026-03-02  2026-03-13   2026-03-17  1 cycle
1.11.0   2026-03-30  2026-04-10   2026-04-14  1 cycle
1.12.0   2026-04-27  2026-05-08   2026-05-12  LTS (12 months)

new export dialog  merged 2026-01-02 -> ships in 1.8.0 on 2026-01-20
crash fix in sync  merged 2026-01-05 -> ships in 1.8.0 on 2026-01-20
faster search      merged 2026-01-06 -> ships in 1.9.0 on 2026-02-17
dark theme         merged 2026-02-10 -> ships in 1.10.0 on 2026-03-17
plugin API         merged 2026-03-02 -> ships in 1.10.0 on 2026-03-17

Note the boundary: a change merged on the cut day itself (crash fix in sync, merged 2026-01-05) is defined here as making that train. Write such rules down; arguments about "was it in before the cut?" are a classic train-release time sink. Most teams make the cut a commit (the branch point), not a time of day.

The release checklist

Automation runs the steps; a checklist makes sure the decisions around them happen. Keep it in the repository (RELEASING.md or an issue template) and tick it for every release; a release-tracking issue per version is a good place.

markdown
## Release 1.9.0 checklist

### Before the cut (owner: release captain)
- [ ] All PRs for the train merged or moved to 1.10 (milestone empty)
- [ ] Unfinished features behind flags, defaulting to off
- [ ] Dependencies updated; no known critical vulnerabilities
- [ ] Release branch `release/1.9` cut from main, CI green

### Stabilisation
- [ ] Release candidate tagged (`v1.9.0-rc.1`) and published to the beta channel
- [ ] Upgrade tested from 1.8.x (data/config migration, rollback to 1.8.x verified)
- [ ] Fixes landed on main first, cherry-picked with `-x`
- [ ] Changelog reviewed by a human: highlights, breaking changes with upgrade steps

### Release day
- [ ] Final tag `v1.9.0` on release/1.9 (annotated, pushed by CI)
- [ ] Pipeline green: all platforms built, checksums, signatures, attestations
- [ ] Artifacts verified from the public download location (`sha256sum -c`)
- [ ] Rollout started (staged: 1% → 10% → 100%), dashboards watched
- [ ] Announcement, docs and website version updated

### After
- [ ] Support window of the previous version updated in SECURITY.md
- [ ] Retrospective: anything to automate or remove from this list?

Rules for a checklist that people actually use:

  • Every item is either automated or a real decision. "Run the tests" belongs in CI, not here; "changelog reviewed by a human" belongs here.
  • Each item has an owner, and one person (the release captain, rotating per release) drives the list.
  • The last item improves the list. Anything done by hand twice is a candidate for automation.

Test yourself

On a release train, a feature isn't finished at the cut-off. What happens?

  1. The release is delayed until it's ready
  2. It ships on the next train; meanwhile it stays off behind a flag
  3. It is merged into the release branch anyway
  4. The train is cancelled

Which item does NOT belong on a manual release checklist?

  1. Changelog reviewed by a human
  2. Run the unit tests
  3. Decide whether the RC is good enough
  4. Confirm the rollback path to the previous version

Why define the cut-off as a commit (the branch point) rather than a time of day?

  1. Git can't record times
  2. It removes arguments about whether a change made the train: it's either an ancestor of the branch point or not
  3. Time zones don't matter
  4. Tags require it