A question to start

Delivery workers don't lift a heavy barrel straight up into a truck. They roll it up a plank. The plank makes the job easier, but does it make it smaller?

The idea

An inclined plane (mặt phẳng nghiêng) is a ramp: a flat surface tilted at an angle. To raise a load to a height hh, you can lift it straight up with a force equal to its weight WW, or push it up a ramp of length LL with a smaller force FF, over a longer distance.

On a smooth ramp (no friction), the work is the same both ways:

FL=Wh⇒F=WhLF L = W h \qquad \Rightarrow \qquad F = W \frac{h}{L}
  • FF: force pushing the load up along the ramp, in N\text{N}
  • LL: length of the ramp, in m\text{m}
  • WW: weight of the load, in N\text{N}
  • hh: height the load is raised, in m\text{m}

The longer and gentler the ramp, the smaller the force. Roads that zig-zag up mountains, wheelchair ramps, and the thread of a screw (a ramp wound round a cylinder) all use this idea.

FW h L
Pushing a box up a ramp of length L needs a force F smaller than its weight W, over a longer distance.

The golden rule of machines

Levers, pulleys, hydraulic presses and ramps all follow the same rule (Galileo called it the golden rule of mechanics):

No simple machine saves work. If it lets you use a smaller force, you must move that force through a proportionally longer distance.

Real machines have friction, so they need more work than the useful work. The efficiency (hiệu suất) compares them:

H=AusefulAtotal×100%H = \frac{A_{\text{useful}}}{A_{\text{total}}} \times 100\%
  • AusefulA_{\text{useful}}: the work you actually need (here WhWh); AtotalA_{\text{total}}: the work you put in (here FLFL)
  • HH is always less than 100%100\% for a real machine

Worked examples

Example 1: a box on the simulation's ramp.

  • Given: a 4 kg4\ \text{kg} box on a smooth ramp L=4 mL = 4\ \text{m} long rising h=2 mh = 2\ \text{m} (a 30∘30^\circ slope). Take g=10 N/kgg = 10\ \text{N/kg}.
  • Find: the force along the ramp that holds the box still (or pushes it up steadily).
  • Formula: F=WhLF = W \dfrac{h}{L}.
  • Solve: W=4×10=40 NW = 4 \times 10 = 40\ \text{N}. F=40 N×2 m4 m=20 NF = 40\ \text{N} \times \dfrac{2\ \text{m}}{4\ \text{m}} = 20\ \text{N}.
  • Answer: F=20 NF = 20\ \text{N}, half the weight.
  • Check: the ramp is twice as long as it is high, so the force is half the weight.

See it in the simulation

The block of Example 1 on a smooth 30∘30^\circ slope with a pull of 20 N20\ \text{N} up the slope. Press Play: it stays at rest, because the pull exactly balances the part of the weight along the slope (mgsin⁡θmg \sin\theta in the readouts, 20 N20\ \text{N}). Set the pull to 19 N19\ \text{N} and it slides down; to 21 N21\ \text{N} and it moves up. Make the slope steeper: a bigger pull is needed.

θ30°mgNFalong the slope: mg sinθ = 20.0 Npull up the slope: F = 20 Nmax static friction μs·N = 0.0 N0.0 N ≤ 0.0 N:the block stays at reststatic friction = 0.0 Nred: forces · dashed: parts of mgblue: velocity · purple: angle

Example 2: loading a barrel.

  • Given: a barrel of mass 60 kg60\ \text{kg} must be raised h=1.0 mh = 1.0\ \text{m} onto a truck using a plank L=3.0 mL = 3.0\ \text{m} long; g=9.8 N/kgg = 9.8\ \text{N/kg}.
  • Find: the force needed if the plank were smooth.
  • Solve: W=60×9.8=588 NW = 60 \times 9.8 = 588\ \text{N}. F=588×1.03.0=196 NF = 588 \times \dfrac{1.0}{3.0} = 196\ \text{N}.
  • Answer: 196 N196\ \text{N}, one third of the weight.
  • Check: FL=196×3.0=588 J=WhFL = 196 \times 3.0 = 588\ \text{J} = Wh.

Example 3: efficiency of the real plank.

  • Given: because of friction, the workers actually push with 250 N250\ \text{N} along the 3.0 m3.0\ \text{m} plank.
  • Find: the efficiency.
  • Solve: Auseful=Wh=588 JA_{\text{useful}} = Wh = 588\ \text{J}; Atotal=FL=250×3.0=750 JA_{\text{total}} = FL = 250 \times 3.0 = 750\ \text{J}. H=588750×100%=78.4%H = \dfrac{588}{750} \times 100\% = 78.4\%.
  • Answer: about 78%78\%. The other 162 J162\ \text{J} becomes heat through friction.
  • Check: less than 100%100\%, as it must be.

Try it: ramp and force meter

You need: a force meter (or a rubber band and ruler), a toy car or a small trolley, a long board, books to prop it up, a ruler.

  1. Weigh the car by hanging it from the meter.
  2. Prop the board on books so that its top end is h=10 cmh = 10\ \text{cm} high. Measure its length LL.
  3. Pull the car slowly up the board with the meter held parallel to the board, and read the force.
  4. Raise the board to 20 cm20\ \text{cm} and repeat.

What you should see: the force is close to WhLW \frac{h}{L} (a little bigger, because of friction), and it roughly doubles when you double the height.

Common mistakes

  • "The ramp means less work." Less force, longer distance, the same work (more, with friction).
  • Using the ramp's length instead of the height in WhWh. The useful work is the weight times the vertical height.
  • Efficiency above 100%100\%. If you get that, you have swapped useful and total work.

Practice

  1. A 500 N500\ \text{N} load is pushed up a smooth ramp 5 m5\ \text{m} long to a height of 1 m1\ \text{m}. What force is needed?
Answer

F=500×15=100 NF = 500 \times \frac{1}{5} = 100\ \text{N}.

  1. A pulley system lifts a 900 N900\ \text{N} load 2 m2\ \text{m}, while the worker does 2250 J2250\ \text{J} of work. What is its efficiency?
Answer

Auseful=900×2=1800 JA_{\text{useful}} = 900 \times 2 = 1800\ \text{J}; H=18002250×100%=80%H = \frac{1800}{2250} \times 100\% = 80\%.

  1. A wheelchair ramp must not need more than 150 N150\ \text{N} to push a 750 N750\ \text{N} wheelchair (ignore friction) up a 0.5 m0.5\ \text{m} step. How long must it be?
Answer

L=WhF=750×0.5150=2.5 mL = \frac{Wh}{F} = \frac{750 \times 0.5}{150} = 2.5\ \text{m}.

Test yourself

A smooth ramp is 4 times as long as it is high. What force pushes a 200 N200\ \text{N} load up it?

  1. 800 N800\ \text{N}
  2. 200 N200\ \text{N}
  3. 50 N50\ \text{N}
  4. 4 N4\ \text{N}

What does the golden rule of machines say?

  1. Machines create energy
  2. No simple machine saves work: less force means more distance
  3. Machines always double the force
  4. Friction helps machines

A machine needs 500 J500\ \text{J} of work to do 400 J400\ \text{J} of useful work. Its efficiency is...

  1. 125%125\%
  2. 80%80\%
  3. 20%20\%
  4. 100%100\%